阿尔基小学扩建及体育馆现代化工程

乙醇小学临时校址

乙醇 小学 School has relocated to the Schmitz Park School interim site for the 2023-24, 2024-25, 2025-26学年.

地址:5000 SW Spokane Street

项目简介

现有的乙醇小学大部分将被拆除. 多层75,000 square foot replacement school will be constructed and the existing gymnasium will remain and be modernized. 现有的西雅图公园部门社区中心将保留.

资金: This project is funded by the Building Excellence V Capital Levy (BEX V), 西雅图选民在2019年通过的法案.

专为当前和未来的学生

The new 乙醇 will provide an equitable learning environment for up to 500 K-5 学生 with inclusive spaces to support its diverse community of 学生 and families. The facility will be constructed of materials and systems that will stand the test of time and  last 75 years or more.

The new building will meet district educational standards for elementary schools, 根据乙醇社区的具体需求进行调整. Input gathered from the 学校设计谘询小组(SDAT) — an advisory group consisting of school leaders, 学生, 父母, and community members — ensures that the design reflects and honors the school personality, 身份, 和社会

The design puts a priority on being easy to navigate for 学生, staff, and 父母. It includes an inviting “front porch” at the new entrance facing the park boulevard, 如何加强与社区和公园的联系.

安全及保安

Visitors will enter through a secure main entrance that invites you into the administrative office for check-in before entering the school. 在上学期间,所有其他的门都将被锁上.

可持续性

The new 乙醇 小学 is being designed to work toward the district’s goals for clean energy and renewable resources and includes the installation of solar panels.

该项目将包括:

  • 所有教室和学习空间都有日光
  • 高效采暖,通风新鲜

建筑材料包括交叉层压木材(CLT), 一种减少整个项目碳足迹的材料.

The Energy Use Index (EUI) for the project is pending with a goal of 15-18.

共享游戏空间

The Seattle Parks Department’s 乙醇 Playfield and parkway is used by 乙醇 小学 School for arrival, 社区集会, and play will be improved as part of the school construction project. 阅读更多.

时间轴

construction phase graphic showing that the school is in the Construction phase
了解在这些项目阶段会发生什么
  • 预设计阶段完成
  • 方案设计阶段完成
  • 设计开发阶段完成
  • 施工文件/许可阶段正在进行中
  • Bid and award phase in progress for rebidding selected bid packages
  • 早期建设活动正在进行中
  • 计划开学时间:2026年9月

项目进展

照片

Aerial view of a construction site with a building in the upper left and construction equipment next to a partially built retaining wall
Aerial view with retaining wall construction in southeast corner – May 2024
a large construction machine with tracks has a giant drill bit and is screwing it into the ground between two metal posts
安装挡土墙桩- 2024年4月
large metal posts approximately 12 feet tall are lined up along a hillside and workers are putting giant wood slabs between them
安装新挡土墙的衬垫——2024年4月
a brick wall on the left faces a partial wall made of steel posts and wood slabs on the right. 在右墙后面的山上可以看到一座房子
Lagging installed for the new retaining wall, looking north – April 2024
a truck labeled "Seattle Tree Care" sites next to a slop with vegetation and houses above. 可以看到一个机械臂伸向植物
为新挡土墙清理景观- 3月. 2024
Aerial view of a large lot with ponding and grass next to a building
Current conditions with grass and temporary erosion control to keep water out of the building – Jan. 2024
一座两层楼建筑附近的草地上有一个池塘. 可以看到一个橙色的建筑围栏.
Temporary erosion control working to avoid run-off of rain water – Dec. 2023
一个开放的区域有草地和橙色的临时织物栅栏
水培草有助控制径流- 11月. 2023
2 workers in construction vests and hats hold hoses while standing in a dirt field. 这块地有一部分是绿色的.
Installing hydroseed to protect the site during the construction pause – Oct. 2023
一幢两层楼房前的一块分级土地
9月,学校场地清理完毕,朝向体育馆. 2023
铲土机正在拆除建筑物的地板
拆除露出了旧地板的一部分. 2023
建筑物的外部,工人在电梯上
Sealing and protecting the existing gym after the school building was removed – Sept. 2023
an excavator is on top of a pile of concrete rubble emptying into a container on a truck
分离和清除拆除碎片- 2023年8月
一台挖掘机正在碾压一座砖砌建筑. 电梯上有一个人在喷水管. 前景的混凝土上有碎石
主楼拆除,向东- 2023年8月
an excavator is crushing a wooden building while a person sprays a hose at it
Demolition of the portable with dust control with hose – August 2023

项目更新

2024年5月- 6月

The Departures process for the new school building is still in progress. School building construction cannot begin until the Departures process is complete and a building construction permit is issued.

离境上诉聆讯已于五月二十八日举行. 该决定预计将于7月初公布.

Installation of the retaining wall on the southeast corner continued through June.

公园大道/游乐场的改善计划正在进行中.

当前的设计

下面的图纸显示了学校目前的设计.

drawing of an aerial view of a large building with a mechanical penthouse. 它上面的一个空间上有彩色的斑点,并标记为“公园路”." Beyond that, a the top of the image is an area marked Seattle Parks and Rec 乙醇 Playground
计划中的学校的建筑师图纸- 2023年6月
architect drawing of a 3 story brick building corner with a breeze way entrance to the left
学校西侧的潜在景观
architects drawing of a 3 story brick building with windows and doors on ground floor and a paved area with people in front
欢迎进入的潜在视图
architect drawing of a person standing in front of a whilte board with younger people sitting at tables
学习区域的潜在视图
建筑师画的人们坐在一堵窗户前
库窗口的潜在视图
一个有门和楼梯的大空间的建筑师图纸
可以看到中央楼梯
建筑师绘制的带有午餐桌的大空间图
公共/用餐区的潜在景观
an architects drawing of a classroom with an adult and a child at a white board
潜在的教室

社区参与

The 基本建设项目及规划 department values insight and input from the school community and neighbors when planning a construction project, 从学校设计顾问团队(SDAT)开始.

使用多种工具,包括电子邮件, 邮件, 传单, 海报, 标志, 社区会议, 以及项目网页. Summary of all communication and engagement during the 乙醇 小学 School planning process.

学校设计谘询小组(SDAT)

在设计过程的早期, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, 父母, and community members. 学生有时被包括在整个或部分过程中. 项目施工经理也参与其中. 了解更多关于乙醇小学SDAT的信息.

项目团队

设计公司: Mahlum建筑师

总承包商/建筑管理公司(GC/CM): 基石总承建商

项目经理:布莱恩·法贝拉, brfabella@weiwei80.com, 206-252-0702

联系

For questions or comments about the project, please use our online feedback form